MOSLER SAFE PLANT, HAMILTON OHIO

Our Environmental Manager for the Ohio Region Mr. Weinstein, was the Certified Professional who prepared two (2) No Further Action (NFA) Letters for a Voluntary Action Program (VAP) cleanup conducted...Read More >

OVERLOOK AT TURKEYFOOT

This project consisted of approximately 50 vertical feet of structural fill placed along a thousand foot long slope to support a vast development of four story hi-rise multifamily buildings. The...Read More >

PARK PLACE AT LYTLE CINCINNATI, OH

Our Environmental Manager for the Ohio Region, Mr. Weinstein was the Certified Professional who oversaw the asbestos remediation of the 370,000 square foot former R.L. Polk building, located in the...Read More >

United States Penitentiary

Patriot Engineering served as a member of the design and construction team for this design-build maximum security United States Penitentiary on the property of the existing USP facility at Terre...Read More >

Union Hospital

This project involved the construction of a 5-story (plus mechanical penthouse) new hospital facility. The footprint of the new hospital covers approximately 180,000 square feet supported upon a full-basement level....Read More >

Blanchfield Army Community Hospital – Addition/Alteration

Provide construction materials testing, inspections and special inspection services Soils, site works- foundation observations and utility backfill testing, proctors, and all soils laboratory testing required by the USACE. Concrete- making...Read More >

CENTER HILL DAM

This project consisted of the rehabilitation of the Center Hill Dam.  Patriot services on the project included the making and testing the compressive strength of cylinders and the performance of...Read More >

Crude Oil Release

During a site inspection in July 2013, the Illinois Environmental Protection Agency (IEPA) discovered approximately 20 barrels of crude oil and at least 25 barrels of formation brine in a...Read More >

Plaquemines Parish School Board Recovery Construction Program

In 2005 Hurricane Katrina devastated the Plaquemine Parish School System.  With the help of the Federal Emergency Management Agency (FEMA), PPSB is undergoing a massive rebuilding of its instructional and...Read More >

PLAINFIELD FIRE STATION # 123

This 4.4 million dollar project consists of a 23,000 sq. ft., 2 story, 4 bay station which will incorporate a 3-story tower for ladder/rope training and will also facilitate confined-space...Read More >

NEW PLAINFIELD HIGH SCHOOL

This project consisted of a new 450,000 square foot High School in Plainfield, Indiana. Patriot operated an onsite field office equipped with a concrete compressive strength testing laboratory. Patriot also...Read More >

LAWRENCE TOWNSHIP FIRE STATION #332

This building was originally built in 1983, but in January 2009 Lawrence Township Station 332, now known as Station 17 underwent a major renovation. The station was redesigned with much...Read More >

JW MARRIOTT HOTEL COMPLEX

The JW Marriott Hotel Complex consists of the new JW Marriott, Springhill Suites and Courtyard and the renovated Fairfield Inn in downtown Indianapolis.  Construction on the three new hotels began...Read More >

COMMUNITY HOSPITAL NORTH

The $170 million expansion, “The Next Evolution in Health Care” officially opened April 2007 and consists of a 6-story patient tower addition, 1,000 car parking garage, 5-story medical office building,...Read More >

CARMEL CITY CENTER

Carmel City Center is a one million square foot, multi-use project in the heart of Carmel, Indiana.  The project is one piece of a master planned redevelopment of downtown Carmel;...Read More >

BALL STATE UNIVERSITY RECREATION & WELLNESS CENTER

The project consisted of an approximately 200,000 square feet recreation and fitness center at Ball State University.  The facility includes a new fitness center, five-court gym, indoor turf field, multi-purpose...Read More >

EDWARDSPORT INTEGRATED GASIFICATION COMBINED CYCLE (IGCC) PLANT

The Edwardsport IGCC Project involved the construction of a new power generation facility on a 300-acre project site in west-central Indiana for Duke Energy. This state-of-the-art power plant generates 618-megawatts...Read More >

CAYUGA FLUE GAS DESULFURIZATION PROJECT

Construction on this project began in May of 2005 on the new sulfur dioxide flue gas desulfurization project at the Duke Energy Generating Station in Cayuga, Indiana. Patriot reported directly...Read More >

ARMY CHEMICAL DEMILITARIZATION FACILITY (NECDF)

The project was initiated and completed in accordance with treaty requirements to neutralize the existing VX nerve agent stockpile that was created and stored at the Newport Chemical Weapons Depot...Read More >

PRAIRIE CORRECTIONAL FACILITY

Patriot was contracted to prepare a mold remediation protocol, assist with bidder selection, provide mold remediation oversight, and pre & post mold remediation IAQ sampling services within B pod, at...Read More >

MUSIC CITY CENTER

Construction began in February 2010 at The Music City Center in Nashville Tennessee. The facility will include a 350,000 square-foot exhibit hall, 59 meeting rooms, two ballrooms, and 36 loading...Read More >

HIGHLAND HEIGHTS

The proposed project includes the expansion of Highland Heights Middle/High School in Nashville, Tennessee.  The current school will be demolished except for the existing four (4) story portion of the...Read More >

VOLKSWAGEN ASSEMBLY PLANT

Located on a 1,350 acre brownfield site, the production facility includes conventional steel framed buildings with concrete columns, roof structures with skylights, metal wall panels with windows, and a single-ply...Read More >

TOYOTA MOTOR MANUFACTURING

Construction began in June, 2007 of an over 1 million square foot manufacturing plant. This included the moving of over 16 million cubic yards of soil, a 40 foot fill...Read More >

MCALPINE LOCK AND DAM

The McAlpine Locks Replacement Project provides for a new 110 foot by 1,200-foot lock to replace the inactive 56-foot by 360 foot lock and the 110 foot by 600 foot...Read More >

KENTUCKY TRANSPORTATION CABINET

This building serves as the new headquarters for the Kentucky Transportation Cabinet (about 1,300 people).  The office building and attached circulation towers enclose approximately 450,000 square feet.  The office building...Read More >

HUMAN RESOURCES CENTER OF EXCELLENCE

The Human Resources Center of Excellence (HRCoE) was the largest construction project ever undertaken at Fort Knox. The six-building, 880,000 square foot complex brings together three commands relocated from other...Read More >

FORT KNOX IBCT BARRACKS

This project involved the construction of four 60,000 square-foot building barracks designed to sleep 600 unaccompanied enlisted personnel. The quad-shaped design creates a center courtyard with green space and the...Read More >

MACKEY ARENA RENOVATION PURDUE UNIVERSITY

This new 130,000 SF three level structure is north of Mackey Arena and extends from the outer edges of Mackey along Northwestern Ave. When complete this structure will have an...Read More >

IPFW PARKING GARAGE NO. 3

This project consisted of the construction of a new parking garage on the north side of the existing Indiana University – Purdue University Fort Wayne (IPFW) campus, to be known...Read More >

FORT WAYNE WASTEWATER TREATMENT PLANT

This project consisted of two phases of construction. Phase No. I construction began on this project in the fall of 2002 and completed in the Fall of 2004. This project...Read More >

FAMILY DOLLAR DISTRIBUTION CENTER NO. 10

Construction began on this 815,000 square foot distribution center in the spring of 2011 and was completed by April 2012.  The Conlan Company served as the construction manager for the...Read More >

EULER SCIENCE COMPLEX TAYLOR UNIVERSITY

The project began in the summer of 2010 with the excavation of the basement level. At a cost of $41.7 million, this 137,000 square foot facility is set to be...Read More >

ALLEN COUNTY WAR MEMORIAL COLISEUM

This project consisted of raising the roof to accommodate the construction of additional seating for the main arena to allow the area’s historic venue to host large events than that...Read More >

TOYOTA MOTOR MANUFACTURING

Patriot Engineering began on this project in early 1997. Patriot has performed testing on over 1.1 billion dollars worth of construction. Patriot has performed auger cast pile inspections, field density...Read More >

OLD NATIONAL BANCORP HEADQUARTERS

This project consisted of construction of a new 251,000 square foot eight story office building along with a three story pavilion and glass atrium. The project also includes a multi-level...Read More >

EVANSVILLE ARENA

Prior to construction in late 2009, Patriot Engineering performed the Geotechnical Investigation for this project. Along with the geotechnical investigation, Patriot performed pile load tests by using strain gages in...Read More >

WC CLEARWELL P12-816

This project included rigorous concrete specifications and testing requirements for the City. Patriot completed the testing with ACI certified technicians on-site and reported results from our AMRL laboratory within twelve...Read More >

ABBOTT LABS

Patriot Engineering - Projects - Ohio - Abbott Labs

This project consisted of over 12 feet of compacted base soil for the massive foundations to support 45 feet tall continuously poured columns.  The poured in place roof was supported...Read More >

HUBER HEIGHTS SCHOOLS

Construction began in June 2010 for five new elementary schools, one middle school, and one high school in the Huber Heights City School District. Patriot was involved with three of...Read More >

GENERAL MOTORS DISTRIBUTION CENTER

Construction began on this 400,000 square foot GM Distribution Center with a fast track schedule for completion in just eight months. Patriot’s services for this project included special inspections, lime...Read More >

DAYTON INTERNATIONAL AIRPORT MULTI-LEVEL PARKING STRUCTURE

The project consisted of a three level 360,000 square feet post-tensioned parking structure. This project required testing for each building component including over 1,500 Geopier observations, soils field density tests,...Read More >

BROADWAY STREET BRIDGE

Patriot provides on call testing services to the City of Dayton for road  projects.      This  demanding  work  includes  deploying, testing, inspecting and returning to the laboratory with samples safely and...Read More >

MAD RIVER AND MIAMI RIVER DRINKING WATER WELL FIELDS

The project included the design and construction of 66 large diameter gravel pack wells, which were completed at the Mad River and Miami River, well fields. The wells produce between...Read More >

SAMMIS FIRST ENERGY PLANT

This 850’ x 90’ desulfurization smoke stack was completed in less than four months. The project consisted of 17,000 cubic yards of continuous concrete placement which requiring constant monitoring and...Read More >

EARLY LEARNING CENTER

This project included a new 66,000 square foot K-2 elementary facility for Trotwood-Madison City School District and the Ohio School Facilities Commission. The single story facility included a brick veneer...Read More >

Neil Armstrong Engineering Building : Purdue University

Construction began for this project in the summer of 2005 and was completed in the fall of 2007. Patriot's primary contact on this project was Mr. Dave Dietrich of the...Read More >

Cinergy FGD Project

Construction on this project began in May of 2005 and is still ongoing. Patriot reports directly to the owner on this project, which is driven by emissions regulations provided by...Read More >

Benton County Wind Farm

Construction began in September 2007 for Indiana's first wind farm in Benton County, Indiana. The project consisted of the construction of 87 turbines spread over 22 square miles of farmland....Read More >

Lucas Oil Stadium

Construction began on this project in October 2005 and completed in August 2008. This project consisted of the construction of a cast-in-place concrete frame to support the pre-cast concrete seating...Read More >